Completed Projects
Page Navigation
-
Completed Projects
- Bella Romero Academy 4-8 School
- Billie Martinez Elementary Project Updates
- Chappelow K-8 Project Updates
- Dos Rios Elementary
- Franklin Middle School
- Greeley West High School
- Harold S. Winograd K-8 School
- Heiman Elementary School
- Jackson Elementary Project Updates
- James Madison STEAM Academy K-8
- Jefferson High School/Career and Technical Education Center
- Jefferson Junior High School/Transitions
- Maplewood Elementary School
- Meeker Elementary School
- Monfort Elementary School
- S. Christa McAuliffe STEM Academy
- Scott Elementary School
- The Tointon Academy of Pre-Engineering
Photos
Headlines
-
Greeley West High School Ground Breaking Ceremony 2020
Officials from Greeley, Evans and Weld County joined leadership from Greeley-Evans School District 6, the Board of Education and members of the Greeley West High School staff for the official breaking of ground at Greeley West High School. Contractor Adolfson and Peterson Construction and architects Hord, Coplan and Macht helped host the event for about 70 people who attended.
-
Greeley West High School Conceptual Flyover
Construction will begin this summer on the new Greeley West High School. Preliminary site and school design was completed in May. A Design Advisory Group composed of teachers, administrators and students at the school provided recommendations and feedback to architects. Most of the existing school will remain in place during construction, and there will be little disruption to learning as the new school is built.
-
Greeley West Design Advisory Group Update
The Greeley West Design Advisory Group met on April 8 for a virtual meeting.. Architects from Hord, Coplan and Macht presented a preliminary schematic design for the new Greeley West High School. The architects presented a video “fly through” of what the exterior and interior of the new school would look like.
-
Greeley West Design Advisory Group Update
Members of the Greeley West Design Advisory Group met Wednesday, February 12 to review the architect's proposed design for how the school will be constructed on the current site.
-
Trade Partner Open House - Greeley West High School Project
You're invited to attend an Open House hosted by Adolfson & Peterson Construction on Tuesday, February 18. This open house will provide general information about the upcoming Greeley West High School project.
Construction Timelapse Videos
Design Advisory Group Reports
-
Report Number 6
This DAG Meeting was conducted as a virtual meeting, utilizing the Zoom platform. The goal of tonight's meeting was to present the updated design for the new Greeley West High School building and site. The DAG included a more focused discussion related to site design amenities.
-
Report Number 5
This DAG meeting was conducted as a virtual meeting, utilizing the Zoom platform. The goal of tonight's meeting was to present the updated design for the new Greeley West High School building and site. The DAG included a more focused discussion related to the classroom wings as well as the Art Classroom spaces.
-
Report Number 4
This meeting is intended to be used to coordinate with District 6 and RLH for the new construction of Greeley West.
-
Report Number 3
The goal of the meeting was to present updated plans of the two selected design options for the new Greeley West High School building and site. These options include more specific programmatic layouts including the locations of all spaces and their adjacencies to other departments. After presenting the two options, the DAG was divided into three groups to evaluate the options and make a recommendation on the preferred solution.
-
Report Number 2
The goal of this meeting was to present four design solutions for the new Greeley West High School building and site. These options include the process for phasing the new construction and sequence of demolition of existing building components. After presenting the four options, the DAG was divided into three groups to evaluate the options and eventually narrow down to the favorite two.
-
Report Number 1
The goal of the January 15, 2020 meeting was to kick off the DAG process for the Greeley West High School project. The agenda included introductions, role of the DAG members, Project Overview, Summary of Vision Statements, Trends in High School design, Overview of Programming, and Next Steps.
Design Advisory Group
-
A Design Advisory Group works with architects to help design major elements of a building or project. It is composed of people from the school's community, including staff, parents and students. The Design Advisory Group holds regular meetings throughout the project. Here is the membership for the Greeley West Design Advisory Group:
Jeff Cranson, Principal
Amy Zulauf, Assistant Principal
Stephen Paulson, Social Studies Department Chair
Jane Burke, Math Teacher
Amy Tuttle, English Department
Jordan Karlberg, Construction Trades Department Chair
Kelly Stephens, Counselor
Tom Nugent, Orchestra Teacher
Barb Broderius, IB Parent
Tony Scott, Science Teacher
Dawn Feinberg, Art
Lane Renouf, Student
James Mathews, Student
Bob Billings, District Athletic Director
Sasha Cohoon, Office Manager
Ryan Walstrom, PE Teacher and Coach
Bond Updates
-
June 2022
The roof abatement at the old school is moving along, although a bit more slowly than contractor’s hoped. Weather, mostly in the form of high winds, have caused some delays. Workers wearing full protective gear are working under tarps to complete the asbestos removal from the roof. This must occur before the old building can be torn down. Because of this project and the delay in tearing down the school, the main parking lot for the new school will not be complete by the time the new Greeley West opens in August. Parking will be available north and south of the new school.
Finishing touches are being completed on the new Greeley West. Landscaping to the west of the school is complete. The state-of-the-are auditorium is nearly finished. And the final equipment and furniture is being installed in the core classroom wing on the north end of the building. The ribbon cutting for the new school is tentatively scheduled for August 9, and will be followed by a public open house and tours.
-
May 2022
Teams from Orion Environmental are removing asbestos in the old Greeley West High School in anticipation of the building being torn down in July. In April, inspectors found additional asbestos in the roof at Greeley West. What was believed to be a two week abatement became a minimum 12-week abatement. Most students finished school on April 29, so teachers could move into the open spaces in the new building, where they continued to work through the end of the school year.
Construction on the new school is near completion and is on schedule. Crews are finishing the interior of the building and working on landscaping to the West. A ribbon cutting ceremony will be held in early August to officially open the new building before students return on August 11.
-
November 2021
The construction of the new Greeley West High School is on schedule and on budget. The interior spaces are now the concentration of construction, as most of the exterior has been finished. The floor in the gymnasium is down and bleachers are being installed. The interiors are being finished on the south Career and Technical Education wing. Tile is up on the walls, bathrooms are nearly finished, flooring is in and walls are painted. Plans are to move those programs from the old building into the new building over spring break, so that demolition of the portables currently housing some of those programs can begin. The auditorium is coming together, and the stage is nearly completed. Classrooms on the north side of the building are under construction.
-
January 2021
Construction at Greeley West is moving along quickly. Prefabricated concrete walls are being raised and secured at the south end of the new school. The new Career and Technical Education classrooms and shops have walls, as well as the new auxiliary gymnasium. There is also an elevator shaft that is now visible. Tubes for radiant floor heat have also been installed in the south wing. The orchestra pit and lower floor of the theater has also been constructed. There is a significant amount of dirt being moved on the site, and a retention pond is being constructed at the northwest corner of the property. As well, the old auxilary gymnasium on the old school has been torn down to make room for the new school. The tennis courts have also been torn out as well as the softball field. These will be moved and rebuilt in a new location.